Construction Updates
Monthly Construction Updates - 2024/2025
























Monthly Construction Updates - 2024/2025
October 2024
Hillview JHS Replacement Campus Project
The Hillview Project is well underway. Building footings and slabs have been poured and steel is now being erected on the new Multi-Purpose Room.
The Hillview Project is well underway. Building footings and slabs have been poured and steel is now being erected on the new Multi-Purpose Room.

Multi-Purpose Building Steel Erection

Hillview Building A Footings

Hillview Groundbreaking Ceremony - September 2023
November 2024
Pictures from November 15th. Framing is moving along as well as steel erection.



December 2024
On December 3rd, the last steel beam was placed. An informal Final Steel Beam Signing & Steel Top Out Event was held. The project is coming along nicely.


January 2025
Pittsburg Unified's main project, the Hillview JHS Replacement Campus Project, is coming along. Although there was some rain over the past month, a lot of progress still has been made with the steel construction.

February 2025
Hillview JHS Replacement Campus Project Updates: Building A (Classroom/Admin Building) is framed up. Building B (MPR) is buttoned up and insulation and drywall are being installed inside. Sitework has started as well.






March 2025
Hillview continues to move along.





April 2025
The construction at Hillview JHS is moving along at a good pace. The interior work is picking up with much of the steel studs being installed. The siding to the MPR is being installed.




May 2025
- The new Multi-Purpose Bldg. (Bldg. B) is about 75% complete, with the exterior finish receiving the colors coats and the interior painting beginning. This building should be near 100% complete this coming September. This building is still on schedule to be fully completed in late November/early December so that the District can then occupy and utilize the facility when the 2025-2026 school year resumes in January 2026.
- The new Admin./Classrooms Bldg. (Bldg. A) is moving along quickly and is about 40% complete. The exterior finish insulation has been installed on the entire building, the main roof is mostly complete, and the lower roofs are in progress. The interior framing is nearly complete, and gyp. board installation has begun. This building is still on schedule to be completed in late November/early December so that the District can then occupy and utilize the facility when the 2025-2026 school year resumes in January 2026.
- Construction of the Public Parking Lot, along with associated hardscape & landscape work, will begin in late May/early June and then be completed in October.
- The new Gym. & Locker Rooms Bldg. (Bldg. C) will be under construction starting this August/September after the existing Gym. & Locker Rooms Bldg., and the existing Cafeteria/Kitchen & MP Bldg., have been demolished. This building is still on schedule to be completed in late July 2026 so that the District can then occupy and utilize the facility when the 2026-2027 school year begins in August 2026.
- Construction of the Staff Parking Lot and AC Paved Playyard, along with associated hardscape & landscape work, will begin in late March 2026 and then be completed in mid-June 2026.




